PHASES OF CONSTRUCTION BREAKDOWN
Congratulations on the purchase of your future home site.

You’ve done the hard work in selecting where to live, now it’s over to us to get the land ready to build on.

1. PLANS & PERMITS
Council and Authority acceptance of documentation including engineering design to allow physical works to commence on site.

2. EARTHWORKS
Preparation of the site to achieve design lot levels including site scrape, shaping of the existing ground and construction of retaining walls if required.

3. SEWER & DRAINAGE
Installation of sewer and drainage to service the development of the stage.

4. ROAD BOXING, KERB & CHANNEL
Prepare the ground and start to construct the lower layers of the road pavement. Install water and gas mains and construct kerb and channel.

5. ELECTRICAL & TELECOMMUNICATIONS
Trench and install electrical and telecommunication services once kerb and channel works are complete.

6. FOOTPATHS & ASPHALT
Prepare the ground in readiness to construct footpaths. Construct footpaths and topsoil nature strips. Construction of middle pavement layers and placement of asphalt.

7. COMPLETION & INSPECTION OF WORKS
Council and Service Authority works inspections and sign off to constructed works including roads and services. Provision of final documentation to Council to facilitate a Statement of Compliance for the development stage.

8. TITLES OFFICE & SETTLEMENT
Registration of individual lots from each stage occurs at the titles office, and your block is now ready for you to settle & start the construction of your new home. Congratulations!

If you have any further questions about titling and construction updates, please get in touch.

STAGE CONSTRUCTION PHASE FORECAST TITLES
Stage 2 4. Road boxing, Kerb & Channel November 2021
Stage 3B 1. Plans & Permits Q1 2022
Stage 3C 1. Plans & Permits Q1 2022
Stage 5A: 1. Plans & Permits Q3 2022
Stage 6B: 4. Road boxing, Kerb & Channel November 2021
Stage 6C 4. Road boxing, Kerb & Channel December 2021
Stage 6F 2. Earthworks Q3 2022

We will continue to keep you updated on construction progress on site. We note that delays can be caused by circumstances beyond our control, such as weather, but we will do all we can to minimise their impact.